| Sector |
Client |
Contract |
Description |
Completion Date |
| Highways |
Carillion-URS |
Huntingdon Railway Viaduct repair scheme |
steel fixing / formwork / concreting |
01 January 2009 |
| Industrial |
Carmac |
Asda Distribution Centre Magna Park Leicestershire |
Steel fixing /formwork for retaining walls Insitu concrete stairs external concrete paving & general groundwork's. |
01 May 2009 |
| Industrial |
Maypine Construction Ltd |
Mill Lane Stoney Stratford |
Steel fixing / formwork / groundwork Inlet and outlet chambers for a river headwalls. |
01 November 2009 |
| Industrial |
Mainland |
Sheep Street Birmingham |
Steel fixing / formwork / groundwork / Suspended floors vehicle washes insitu stair flights and general shuttering. |
01 January 2009 |
| Industrial |
Carmac |
Toys R Us Kempston Bedford |
Steel fixing /formwork / groundwork Retaining walls various shuttering including stair flights industrial size areas of concreting making templates and installation of holding down bolts. |
01 March 2009 |
| Highways |
Aggregate Industries |
A6 Rushden Bypass |
Abutment walls for 2 bridges. |
01 August 2009 |
| Paving |
Fitzpatrick |
IO Centre Coventry Business Park Coventry |
External works including kerbing and external concrete yards slabs |
01 December 2009 |
| Paving |
O'Brian |
J&W Camping Suppliers Portmadog Wales |
3000m2 200mm th Concrete slab incl mesh finish & saw cutting. |
01 December 2009 |
| Paving |
O'Brian |
Terex Prologis Park Coventry. |
5000 m2 200mm th Concrete slab incl mesh finish & saw cutting. |
01 December 2009 |
| Paving |
Mainland |
Trinity Mirror Press Facility Erdington Birmingham |
External works including line drainage kerbing hard landscaping and external yard slabs. |
01 May 2009 |
| Paving |
McNicholas |
Max Park Corby |
Insitu concrete structural topping to mezzanine floor. |
01 May 2009 |
| Industrial |
Weldon |
Max Park Corby |
Surface water drainage filter drains |
01 April 2009 |
| Paving |
Twintec |
Liebehr Biggleswade |
10000 m2 10m wide bays 275mm th insitu concrete slab |
01 June 2009 |
| Paving |
Twintec |
Quinn Glass Elton |
Shuttering welded joints on internal insitu concrete slabs. |
01 June 2009 |
| Commercial / Industrial |
Mainland |
New Industrial Units Boundary Road Brackley Northamptonshire |
Foundations External works including kerbing drainage external yard slabs and block paving. |
01 June 2009 |
| Industrial |
GB Construction Ltd |
Nissan Technology Centre Cranfield. |
6000m2 Car park footpaths bike & storage areas |
01 June 2009 |
| Commercial / Industrial |
Hanson |
New Production Depot and Hard standing at Pollington Yorkshire. |
New aggregate bays foundations and drainage to Production Building ramps to silos and hoppers storm & foul drainage power floated insitu concrete floor slabs 13000m2 of external insitu concrete paving. |
01 May 2009 |
| Education |
Galliford Try Plc |
Redevelopment of Harlington Secondary Modern School
Phase 1 |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 December 2009 |
| Highways |
Carillion-URS |
Statue Base Bedford A421 |
Reinforced concrete bases foundations & superstructure for Roundabout Statue on the A421. |
01 November 2009 |
| Paving |
Flatbase |
Morrisons Northampton |
6000 m2 of concrete internal & external concrete paving with power floated finish. |
01 September 2009 |
| Leisure |
Leadbitter Construction Ltd |
Thrapston & District Community Centre Thrapston Northamptonshire. |
Drainage Groundworks Insitu Concrete Shear Walls & 2 Swimming Pool structures including external works. |
01 June 2009 |
| Commercial / Industrial |
Aggregate Industries |
Upgrading Concrete Production Plants in Mansfield Kidderminster & Colwick |
Drainage device ducts concrete paving and structures. |
01 December 2009 |
| Housing |
Barry Howard Homes |
White Lodge Farm - Redevelopment |
3nr Barn Conversions including new concrete floor drainage external works & access road construction. |
01 February 2009 |
| Commercial / Industrial |
Aggregate Industries |
Storage Yard Normanton Air Field Lincolnshire. |
13000 m2 of external insitu concrete paving. |
01 December 2009 |
| Paving |
Aggregate Industries |
Baston Fen |
Repairs to external paving & drainage |
01 February 2009 |
| Housing |
Barry Howard Homes |
New House
Flore |
External paving installation of swimming pool & drainage to new individual house. |
01 June 2009 |
| Housing |
Kings Oak |
New Housing Development for KingsOak Banbury Buckinghamshire. |
New road infrastructure to large housing development including deep drainage & kerbing. |
01 October 2009 |
| Paving |
Fosseway Flooring |
Morrisons Burton Latimer |
8000 sq metres of external concrete paving |
01 January 2009 |
| Housing |
JDR Developments |
Redevelopment of Hilltop Caravan Park Princethorpe Warwickshire. |
New infrastructure of residential caravan parking including caravan bases roads & drainage. |
01 April 2009 |
| Highways |
Carillion-URS |
Road repairs on the A5 at Hockcliffe Hertfordshire. |
Kerb realignment new infrastructure for traffic signal renewals & pavement alterations. |
01 March 2009 |
| Education |
Galliford Try Plc |
Redevelopment of Harlington Secondary Modern School
Phase 2 Harlington Bedfordshire |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 February 2009 |
| Highways |
Carillion-URS |
A14 Girton Cambridgeshire. |
Foundations & erection of new motorway signage |
01 March 2009 |
| Highways |
R&H Investments |
Pavement Crossovers along A5 at Hockliffe |
Expose existing services in pavements relocate and lay new kerbs and tarmac to form entrances onto highway. |
01 March 2009 |
| Highways |
Carillion-URS |
A14 Safety Signs Huntingdon |
Foundations & erection of new motorway signage |
01 March 2009 |
| Paving |
Martyn England |
External concrete paving at Bridgewater |
10000m2 of External concrete paving with a tamp finish. |
01 April 2009 |
| Highways |
Carillion-URS |
A14 Replacement Sign Brampton Hut to Thrapston. |
Removal and replacement of existing road signage. |
01 October 2009 |
| Paving |
Bradcott Construction |
External paving to New Nursing Home Corby |
Paths & Paving |
01 June 2009 |
| Commercial / Industrial |
Thomas Vale |
Warehouse Extension to Crowfoot Carriers Bradwell Hinckley |
Foundations External works including kerbing drainage external yard slabs and block paving. |
01 August 2009 |
| Industrial |
Fuch |
Alumasc Burton Latimer |
New foundation bases for 4nr tanks |
01 July 2009 |
| Housing |
Sterling Construction Management |
Church Street Wellingborough |
Foundation drainage and paving to new terraced houses. |
01 October 2009 |
| Leisure |
Rockingham Construction |
Swimming Pool and Gymnasium extension |
Concrete Pool Structure. |
01 October 2009 |
| Highways |
Carillion-URS |
Crossovers A14 Northamptonshire. |
Provision of 3 emergency vehicle crossovers in the central reservation between J1 A14 and M6M1 junctions |
01 June 2009 |
| Housing |
Sterling Construction Management |
Groundworks for SCM |
Several local groundwork project associated with housing. |
01 November 2009 |
| Highways |
Aggregate Industries |
Boundary Walls Spon End Coventry Warwickshire. |
Major boundary walls structure - 2.5m high to form leisure area adjacent to highway. |
01 September 2009 |
| Housing |
Sterling Construction Management |
Bath Road Kettering |
New roads drainage $ services for new starter home development. |
01 November 2009 |
| Highways |
Carillion-URS |
Road realignment to existing roundabout on the A5 at Milton Keynes |
Kerb & pavement realignment incl alterations to services |
01 September 2009 |
| Industrial |
Wastecom |
New Infrastructure to New Waste Reclamination Plant at Telford Way Kettering |
External drainage kerbing and regrading levels for new waste control depot. |
01 September 2009 |
| Small works |
Private |
New house at Hatton Park Road Wellingborough |
Installation of service ducts along with water and gas services to a new development |
01 December 2009 |
| Commercial / Industrial |
Aggregate Industries |
Road repairs at Earith Cambridgeshire. |
Repairing edge of highway and placement of new kerbs and associated drainage. |
01 October 2009 |
| Highways |
Aggregate Industries |
County Hall Cambridge |
Sundry alterations to external works |
01 October 2009 |
| Highways |
Carillion-URS |
Area Depot Whittlesford |
New pumping chambers for existing pump main. |
01 October 2009 |
| Education |
Thomas Vale Construction |
New Primary School Upton Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Leisure |
Multibuild |
20 bed Extension to the Travel Inn Hotel Kettering Northamptonshire |
Groundworks associated with a 20 bedroom extension to the Travel Lodge and complete with alterations to existing carpark and drainage connections. |
01 January 2009 |
| Highways |
Carillion-URS |
New Motorway Signage M11 |
Providing Signs and Markings for Road User Safety |
01 November 2009 |
| Highways |
Carillion-URS |
New Drainage Scheme - A5 Friars Walsh Bedfordshire |
Resurfacing scheme and associated drainage works |
01 February 2009 |
| Highways |
Aggregate Industries |
Road repairs Witchford Cambridge |
Repairing edge of roadway and placement of kerbs and drainage. |
01 October 2009 |
| Housing |
Miller Homes |
New Housing development at Upton Grange Northampton |
Housing foundations drainage external works & roads etc |
01 April 2009 |
| Education |
Mansell Plc |
New St James Primary School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls foul & storm drainage foundations services & associated external works |
01 February 2009 |
| Education |
Thomas Vale |
Warren Hills Primary School Coalville Warwickshire. |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 August 2009 |
| Education |
Galliford Try Plc |
Sunnyside Primary School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 July 2009 |
| Education |
Galliford Try Plc |
Kings Heath Primary School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 February 2009 |
| Education |
Galliford Try Plc |
Blackthorn Primary School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Education |
Galliford Try Plc |
New Green Oaks Primary School Kingsheath Northampton. |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 December 2009 |
| Education |
Galliford Try Plc |
New Woodvale Primary School Goldings Northampton. |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls foul & storm drainage foundations services & associated external works |
01 July 2009 |
| Small works |
Galliford Try Plc |
Mereway Community College |
New temporary access road |
01 April 2009 |
| Education |
Galliford Try Plc |
The Arbours School Northampton. |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 August 2009 |
| Education |
Galliford Try Plc |
Hunsbury Park School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Housing |
Jackson Carter |
Weldon Housing Project |
8 Unit Housing Developments including groundwork's drainage external works. |
01 January 2009 |
| Highways |
Carillion-URS |
A5/A509 Milton Keynes |
Road Sign replacement |
01 March 2009 |
| Paving |
Flatbase |
Kempston Way Luton |
6000m2 External concrete paving |
01 May 2009 |
| Education (extension) |
Galliford Try Plc |
Harlington Phase 3 |
Return visit to complete the courtyard and further external works and associated drainage. |
01 April 2009 |
| Small works |
Mitie Floors |
Airport Way Luton |
Breakout and replace concrete slabs. |
01 May 2009 |
| Highways |
Carillion-URS |
A5 Duncote/Ashcote Road Junction |
Repairs to kerbs and repairs to drainage adjacent to the highways. |
01 March 2009 |
| Small works |
Hanson |
Remedial works to concrete plant at Kettering Northamptonshire. |
Repairs to kerbs drainage external concrete slabs and new palisade fencing. |
01 June 2009 |
| Paving |
Re-Bau |
Lidl Kettering |
Block paving and kerbing |
01 May 2009 |
| Education |
Galliford Try Plc |
Lings Primary School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 June 2009 |
| Paving |
Flatbase |
Rushden |
Laying concrete yard |
01 June 2009 |
| Small works |
Galliford Interiors |
One Stop Shop Abbey Street Daventry Northamptonshire. |
Removal and replacement of existing External Pavement Works |
01 August 2009 |
| Education |
Galliford Try Plc |
Parklands Primary School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 March 2009 |
| Industrial |
Aggregate Industries |
Stoneflair Newark |
Covered Fuel Bund |
01 October 2009 |
| Education (new) |
Leadbitter Construction Ltd |
New Tresham College Barton Road Kettering Northants |
Installation of the service trenches around the perimeter of the site. |
01 October 2009 |
| Small works |
Aggregate Industries |
Dunton Bassett Leicestershire |
Kerbing |
01 August 2009 |
| Small works |
Silo Services |
Hanson Premix Redditch |
Insitu concrete base |
01 July 2009 |
| Housing |
Inspace |
New Social Housing Hereward Hall Cambridgeshire |
New housing development - groundwork's package - Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Housing |
Inspace |
New Social Housing Chatteris Cambridgeshire |
New housing development - groundwork's package. Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Education |
Galliford Try Plc |
Simon de Senlis School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Education |
Galliford Try Plc |
Lyncrest School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 February 2009 |
| Highways |
Carillion-URS |
A43 Whitfield Turn |
Maintenance Hard standing |
01 November 2009 |
| Education |
Galliford Try Plc |
New Northampton School for Girls Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls foul & storm drainage foundations services & associated external works |
01 September 2009 |
| Industrial |
Prestige Concrete |
Prepour Services Watford Village |
New concrete paving |
01 September 2009 |
| Small works |
Galliford Interiors |
One Stop Shop Abbey Street Daventry Northamptonshire. |
Removal and replacement of existing External Pavement Works |
01 November 2009 |
| Highways |
Carillion-URS |
A1 Blunham Northbound |
Signage |
01 September 2009 |
| Highways |
Carillion-URS |
A1 Sandy Northbound Central Reservation |
Signage |
01 October 2009 |
| Highways |
Carillion-URS |
A43 Evenly Roundabout |
Installation of Emergency Vehicle Hard standing |
01 January 2009 |
| Housing |
Inspace |
External Walls (Polarwall) March Cambridgeshire. |
Installation of external walls using the new innovation walling system - Polarwall |
01 April 2009 |
| Education |
Galliford Try Plc |
St Lukes Primary School Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls foul & storm drainage foundations services & associated external works |
01 October 2009 |
| Highways |
Carillion-URS |
M11 Area 8/Screwfast |
Installation of Screw fast signage |
01 December 2009 |
| Highways |
Carillion-URS |
Newport Pagnell Depot M1 Northbound |
Extension to an existing maintenance pit. |
01 December 2009 |
| Leisure |
Multibuild |
New Travel Lodge Thetford Norfolk |
Groundworks associated with construction of a new Travel Lodge and Public House including carpark drainage and external works. |
01 January 2009 |
| Education (extension) |
Galliford Try Plc |
Whitehills Primary School Northampton |
Obtaining licences etc and carrying out the works for temporary highway crossovers for site access. |
01 January 2009 |
| Education (extension) |
Galliford Try Plc |
Abington Vale Primary School Northampton |
Obtaining licences etc and carrying out the works for temporary highway crossovers for site access. Together with external paving works. |
01 January 2009 |
| Highways |
Carillion-URS |
A5 River Ouse Old Stratford |
Remedial work to existing drainage scheme |
01 February 2009 |
| Highways |
Carillion-URS |
M1 Northbound Jct 12 & 13 Chevron Scheme |
Signage |
01 January 2009 |
| Housing |
Inspace |
New Social Housing Arbury Park E1 Cambridge Cambridgeshire |
New Housing Development - groundwork's package. Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Housing |
Inspace |
New Social Housing Arbury Park E2 Cambridge Cambridgeshire |
New Housing Development - groundwork's package. Enabling works temporary site set up temporary haul roads reduce level dig retaining walls internal insitu concrete floor slabs foul & storm drainage foundations services & associated external works |
01 April 2009 |
| Education (extension) |
Galliford Try Plc |
Queen Eleanor School Northampton |
Obtaining licences etc and carrying out the works for temporary highway crossovers for site access. |
01 February 2009 |
| Highways |
Carillion-URS |
Hard standings M1 Northamptonshire |
Forming Vehicle Mobile Sign (VMS) hard standing adjacent the carriageway. |
01 February 2009 |
| Highways |
Aggregate Industries |
M1 Jct 24 Northbound Signage Works |
New Signage |
01 February 2009 |
| Paving |
Hanson |
Remedial works to concrete plant at Cople Bedfordshire. |
The removal and replacement of approximately 3000m2 of external concrete paving at the Premix Concrete Plant |
01 March 2009 |
| Highways |
Carillion-URS |
A14 Cambridgeshire |
Sign Bins |
01 March 2009 |
| Highways |
Carillion-URS |
A14 |
VMS Hard standing |
01 February 2009 |
| Highways |
Carillion-URS |
New Signage A14 Jct 19 |
Removal and replacement of existing road signage. |
01 March 2009 |
| Highways |
Carillion-URS |
New Signage A14 Cambridgeshire |
Removal and replacement of existing road signage. |
01 March 2009 |
| Highways |
Galliford Try Plc |
Briar Hill School |
Crossovers |
01 March 2009 |
| Housing |
Trak Projects |
Cholsey Oxfordshire. |
Internal slab for barn conversions |
01 May 2009 |
| Housing |
Mansell Plc |
Refurbishment of Orient House Kettering Northamptonshire |
Groundworks drainage services & external works |
01 August 2009 |
| Housing |
Crestel |
Melton Mowbray Leicestershire |
Enabling works |
01 August 2009 |
| Small works |
T & B Contractors |
Oaklands College St Albans |
Floor Slabs |
01 August 2009 |
| Commercial / Industrial |
Lindum Sturgeon |
New Office Block Cygnet Park Hampton Peterborough |
Enabling works temporary site set up temporary haul roads reduce level dig foul & storm drainage foundations services & associated external works |
01 February 2009 |
| Highways |
Carillion-URS |
Verge scalpins A1 Cambridgeshire. |
Remove verge scalpins to reduce level adjacent to the carriageway. |
01 September 2009 |
| Highways |
Carillion-URS |
A428 Croxton signs |
Replacement signs |
01 September 2009 |
| Highways |
Carillion-URS |
New signs A1 Cambridgeshire. |
Removal and replacement of existing road signage. |
01 November 2009 |
| Housing |
Wheatley Winton Hayes |
New Flats Ampthill Road Bedford Bedfordshire. |
Foundations drainage ground floor slabs and external works. |
01 June 2009 |
| Small works |
Carillion-URS |
Whittlesford Depot |
Trial holes for car park |
01 October 2009 |
| Highways |
JME Civils |
Little Stanion Northamptonshire. |
Infrastructure for new housing development site comprising of new mains drainage. |
01 May 2009 |
| Highways |
Carillion-URS |
A14 j18-j19 |
survey works |
01 September 2009 |
| Education |
Galliford Try Plc |
New Duston Eldean School Duston Northampton. |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls foul & storm drainage foundations services & associated external works |
01 October 2009 |
| Highways |
Carillion-URS |
A428 ditch work |
ditch clearance |
01 September 2009 |
| Highways |
Mainland |
New Retail Park Rockingham Road Corby Northamptonshire |
Site haul roads drainage foundations internal & external services site roads crossover & external works |
01 October 2009 |
| Highways |
Carillion-URS |
A428 Barford r/about |
replacement signs |
01 October 2009 |
| Highways |
Carillion-URS |
A1 Huntingdon |
New slip road |
01 October 2009 |
| Small works |
HBH Building Contractors |
Christ Church Smeeton Westerby Leicestershire. |
Installation of a new septic tank associated drainage and external paving. |
01 November 2009 |
| Highways |
Carillion-URS |
Whittlesford Depot |
New car park and access road |
01 October 2009 |
| Highways |
Carillion-URS |
A14 Girton Interchange |
Repairs to Embankment |
01 October 2009 |
| Highways |
Carillion-URS |
A1 Beeston |
Construction of land drain |
01 October 2009 |
| Highways |
Carillion-URS |
A1M j8 |
Replace drain manhole and gullies |
01 October 2009 |
| Highways |
Carillion-URS |
A14 j17-j19 |
Ditch clearance works adjacent to the highway |
01 October 2009 |
| Highways |
Carillion-URS |
Verge scalpins A1 Cambridgeshire. |
Verge scalpins removal to side of highways. |
01 January 2009 |
| Highways |
Carillion-URS |
M45 Earthwork |
Remedial works to kerb |
01 November 2009 |
| Highways |
Aggregate Industries |
RAF Croughton |
Car park and pavement reconstruction including associated drainage. |
01 January 2009 |
| Leisure |
SDC Construction |
Bletchley Leisure Centre |
Temporary car park and associated services and drainage. |
01 January 2009 |
| Highways |
Carillion-URS |
M1 Birchanger |
Ditch work clearance |
01 February 2009 |
| Highways |
Carillion-URS |
A1M j8 |
Additional 200m of replacement drain |
01 February 2009 |
| Industrial |
Prestige Concrete |
Prepour's new service yard. |
Preparation and adjustment of level for the new concrete slab and installation of new drainage system |
01 March 2009 |
| Leisure |
SDC Construction |
Bletchley Leisure Centre |
Reduce level dig etc site set up haul roads drainage foundations services & external works |
01 December 2009 |
| Highways |
SDC Construction |
Princes Way Bletchley Buckinghamshire |
278 & 104 Highway Works - Realignment of the carrigeway to Princes Way and associated services & drainage works |
01 December 2009 |
| Highways |
Carillion-URS |
A14 - j17 to j19 |
Ditch and verge clearance adjacent to the highways. |
01 April 2009 |
| Leisure |
SDC Construction |
New Hotel Banbury |
Site access and haul roads |
01 March 2009 |
| Housing |
Crestel |
New Housing Estate Shefford Bedfordshire. |
General civils works including on and off site drainage roads and external works |
01 November 2009 |
| Housing |
F E Peacock Construction Ltd |
New Housing Estate Barrowden Northamptonshire. |
Reduce level dig etc site set up haul roads drainage foundations services road crossover & external works |
01 September 2009 |
| Housing |
F E Peacock Construction Ltd |
Survey March |
Investigation Survey |
01 June 2009 |
| Education |
Galliford Try Plc |
Greenfield Special School Greenfields Northampton |
Enabling works temporary site set up temporary haul roads reduce level dig retaining walls foul & storm drainage foundations services & associated external works. |
01 June 2009 |
| Highways |
Carillion-URS |
A14 drainage remedials |
Removal & replacement of drainage system |
01 June 2009 |
| Small works |
Waker |
SED |
Temporary insitu concrete hard standing for display |
01 May 2009 |
| Housing |
F E Peacock Construction Ltd |
4 Flats Deeping St James Lincolnshire. |
Reduce level dig etc site set up haul roads drainage foundations services road crossover & external works |
01 February 2009 |
| Highways |
Lafarge |
Stamford |
Sundry highways works adjusting kerbs manholes etc |
01 July 2009 |
| Highways |
Lafarge |
A15 Walcott |
Sundry highways works adjusting kerbs manholes etc |
01 July 2009 |
| Highways |
Lafarge |
A45 Northampton |
Sundry highways works adjusting kerbs manholes etc |
01 July 2009 |
| Highways |
Lafarge |
Pinch beck |
Sundry highways works adjusting kerbs manholes etc |
01 July 2009 |
| Leisure |
SDC Construction |
Bletchley Leisure Centre Concrete Floor Slabs Milton Keynes |
Insitu concrete slabs to high tolerance to the 2nd 1st & ground floors. |
01 December 2009 |
| Highways |
Galliford Try Plc |
Standens Barn |
Reinstatement of crossovers |
01 June 2009 |
| Highways |
Galliford Try Plc |
Bellinge |
Reinstatement of crossovers |
01 June 2009 |
| Commercial / Industrial |
Galliford Try Plc |
Northampton Water Treatment Plant Little Billing Northampton. |
Major service ducts and drainage infrastructure for new water treatment plant. |
|
| Commercial / Industrial |
Watson & Cox (Construction) Ltd |
Galvanising Plant Sawtry Cambridgeshire. |
Site haul roads drainage foundations internal & external concrete slabs services site roads new highway access road crossover & external works |
|
| Industrial |
HBH Building Contractors |
Highways Drainage Draughton |
Highways drainage |
01 January 2009 |
| Industrial |
Galliford Try Plc |
Remedial works to estate roads Arbury park Cambridge |
Replacement of kerbs etc |
01 March 2009 |
| Commercial / Industrial |
SDC Construction |
University Centre Peterborough. |
Site haul roads drainage foundations internal & external concrete slabs services site roads new highway access road crossover & external works |
|
| Commercial / industrial |
Galliford Try Plc |
Amenities Building Corby Cube Corby Northamptonshire |
Forming of a new macadam & paved pedestrian walkway for access to a new swimming pool and attendance to site works. |
|
| Small works |
Galliford Try Plc |
Duston & Kingsley School remedials |
Snagging work to other groundwork subcontractor works. |
01 May 2009 |
| Highways |
Carillion-WSP |
A14 Kettering Northampton. |
Replacement and installation of road signs |
|
| Housing |
SDC Construction |
Sheltered Housing Witham Essex. |
traditional foundations services drainage & car parks |
|
| Small works |
Watson & Cox (Construction) Ltd |
Northfield Avenue |
External works associated with the construction of a new Retail park. |
|
| Industrial |
Mainland |
Sheep Street, Birmingham |
Steel fixing / formwork / groundwork / Suspended floors, vehicle washes, insitu stair flights and general shuttering. |
11 January 2007 |
| Paving |
Mainland |
Trinity Mirror Press Facility, Erdington, Birmingham |
External works including line drainage, kerbing, hard landscaping and external yard slabs. |
02 May 2008 |
| Commercial / Industrial |
Mainland |
New Industrial Units, Boundary Road, Brackley, Northamptonshire |
Foundations, External works including kerbing, drainage, external yard slabs and block paving. |
19 June 2008 |
| Industrial |
GB Construction Ltd |
Nissan Technology Centre, Cranfield. |
6,000m2 Car park, footpaths, bike & storage areas |
26 June 2008 |
| Commercial / Industrial |
Hanson |
New Production Depot and Hard standing, at Pollington, Yorkshire. |
New aggregate bays, foundations and drainage to Production Building ramps to silos and hoppers, storm & foul drainage, power floated insitu concrete floor slabs, 13000m2 of external insitu concrete paving. |
02 May 2009 |
|
Galliford Try Plc |
Redevelopment of Harlington Secondary Modern School |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 December 2008 |
|
|
Phase 1 |
|
|
| Leisure |
Leadbitter Construction Ltd |
Thrapston & District Community Centre, Thrapston, Northamptonshire. |
Drainage, Groundworks, Insitu Concrete Shear Walls & 2 Swimming Pool structures including external works. |
02 June 2008 |
| Housing |
Barry Howard Homes |
White Lodge Farm - Redevelopment |
3nr Barn Conversions, including new concrete floor, drainage, external works & access road construction. |
02 February 2009 |
| Housing |
Kings Oak |
New Housing Development for KingsOak, Banbury, Buckinghamshire. |
New road infrastructure to large housing development including, deep drainage & kerbing. |
02 October 2009 |
| Education |
Galliford Try Plc |
Redevelopment of Harlington Secondary Modern School |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 February 2010 |
|
|
Phase 2, Harlington, Bedfordshire |
|
|
| Highways |
Carillion - URS |
A14 Replacement Sign, Brampton Hut to Thrapston. |
Removal and replacement of existing road signage. |
02 October 2009 |
| Education |
Thomas Vale Construction |
New Primary School, Upton, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 April 2011 |
| Housing |
Miller Homes |
New Housing development at Upton Grange, Northampton |
Housing foundations, drainage, external works & roads etc |
02 April 2010 |
| Education |
Mansell Plc |
New St James Primary School, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, foul & storm drainage, foundations, services & associated external works |
02 February 2010 |
| Education |
Galliford Try Plc |
Sunnyside Primary School, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 July 2011 |
| Education |
Galliford Try Plc |
Kings Heath Primary School, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 February 2011 |
| Education |
Galliford Try Plc |
New Green Oaks Primary School, Kingsheath, Northampton. |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 December 2010 |
| Education |
Galliford Try Plc |
New Woodvale Primary School, Goldings, Northampton. |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, foul & storm drainage, foundations, services & associated external works |
02 July 2011 |
| Education |
Galliford Try Plc |
The Arbours School, Northampton. |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 August 2011 |
| Education |
Galliford Try Plc |
Hunsbury Park School, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 April 2011 |
| Housing |
Jackson Carter |
Weldon Housing Project |
8 Unit Housing Developments including groundwork's, drainage, external works. |
02 January 2011 |
| Education |
Galliford Try Plc |
Parklands Primary School, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 March 2011 |
| Housing |
Inspace |
New Social Housing, Hereward Hall, Cambridgeshire |
New housing development - groundwork's package - Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 April 2011 |
| Housing |
Inspace |
New Social Housing, Chatteris, Cambridgeshire |
New housing development - groundwork's package. Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 April 2011 |
| Education |
Galliford Try Plc |
Simon de Senlis School, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 April 2011 |
| Education |
Galliford Try Plc |
New Northampton School for Girls, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, foul & storm drainage, foundations, services & associated external works |
02 September 2012 |
| Housing |
Inspace |
External Walls (Polarwall), March, Cambridgeshire. |
Installation of external walls using the new innovation walling system - Polarwall |
02 April 2011 |
| Education |
Galliford Try Plc |
St Lukes Primary School, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, foul & storm drainage, foundations, services & associated external works |
02 October 2011 |
| Highways |
Carillion - URS |
Hard standings, M1, Northamptonshire |
Forming Vehicle Mobile Sign (VMS) hard standing adjacent the carriageway. |
02 February 2011 |
| Housing |
Inspace |
New Social Housing, Arbury Park E1, Cambridge, Cambridgeshire |
New Housing Development - groundwork's package. Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 April 2011 |
| Housing |
Inspace |
New Social Housing, Arbury Park E2, Cambridge, Cambridgeshire |
New Housing Development - groundwork's package. Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, internal insitu concrete floor slabs, foul & storm drainage, foundations, services & associated external works |
02 April 2011 |
| Highways |
Carillion - URS |
New Signage, A14, Cambridgeshire |
Removal and replacement of existing road signage. |
02 March 2011 |
| Housing |
Mansell Plc |
Refurbishment of Orient House, Kettering, Northamptonshire |
Groundworks, drainage, services & external works |
09 August 2012 |
| Commercial / Industrial |
Lindum Sturgeon |
New Office Block, Cygnet Park, Hampton, Peterborough |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, foul & storm drainage, foundations, services & associated external works |
02 February 2012 |
| Highways |
Carillion - URS |
Verge scalpins, A1 Cambridgeshire. |
Remove verge scalpins to reduce level adjacent to the carriageway. |
08 September 2011 |
| Highways |
Carillion - URS |
New signs, A1 Cambridgeshire. |
Removal and replacement of existing road signage. |
08 November 2011 |
| Highways |
JME Civils |
Little Stanion, Northamptonshire. |
Infrastructure for new housing development site, comprising of new mains drainage. |
02 May 2012 |
| Education |
Galliford Try Plc |
New Duston Eldean School, Duston, Northampton. |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, foul & storm drainage, foundations, services & associated external works |
02 October 2012 |
| Highways |
Mainland |
New Retail Park, Rockingham Road, Corby, Northamptonshire |
Site haul roads, drainage, foundations, internal & external, services, site roads, crossover & external works |
08 October 2011 |
| Highways |
Carillion - URS |
Whittlesford Depot |
New car park and access road |
08 October 2011 |
| Highways |
Carillion - URS |
A14 J17-j19 |
Ditch clearance works adjacent to the highway |
08 October 2011 |
| Highways |
SDC Construction |
Princes Way, Bletchley, Buckinghamshire |
278 & 104 Highway Works - Realignment of the carrigeway to Princes Way and associated services & drainage works |
02 December 2012 |
| Highways |
Carillion - URS |
A14 - J17 to J19 |
Ditch and verge clearance adjacent to the highways. |
02 April 2012 |
| Housing |
Crestel |
New Housing Estate, Shefford, Bedfordshire. |
General civils works including on and off site drainage, roads and external works |
02 November 2012 |
| Housing |
F E Peacock Construction Ltd |
New Housing Estate, Barrowden, Northamptonshire. |
Reduce level dig etc, site set up, haul roads, drainage, foundations, services, road, crossover & external works |
02 September 2012 |
| Education |
Galliford Try Plc |
Greenfield Special School, Greenfields, Northampton |
Enabling works, temporary site set up, temporary haul roads, reduce level dig, retaining walls, foul & storm drainage, foundations, services & associated external works. |
02 June 2013 |
| Commercial / Industrial |
Galliford Try Morrison (GTM) |
Northampton Water Treatment Plant, Little Billing, Northampton. |
Major underground service duct system and drainage infrastructure for new Sludge Treatment Centre. |
02 October 2013 |
| Commercial / Industrial |
Watson & Cox (Construction) Ltd |
Galvanising Plant, Sawtry, Cambridgeshire. |
Site haul roads, drainage, foundations, internal & external concrete slabs services, site roads, new highway access road, crossover & external works |
02 July 2013 |
| Education |
SDC Construction |
University Centre, Peterborough. |
Site haul roads, drainage, foundations, internal & external concrete slabs services, site roads, new highway access road, crossover & external works |
02 December 2013 |
| Housing |
SDC Construction |
Sheltered Housing, Witham, Essex. |
traditional foundations, block & beam floors,services, drainage, car parks, externals. |
|
| Leisure |
SDC Construction |
Bletchley Leisure Centre |
Bulk earthworks, foundations & groundfloor slabs, isitu concrete superstructure floor slabs, drainage- adopted and private, services, access roads, hard landscaping, multi storey car park. |
|
| Highways |
Carillion - WSP |
Wooley |
Ditch Clearance & regrading, head wall installation |
02 November 2013 |
| Highways |
Carillion - WSP |
A14 J19-J34 Sign Renewal |
Replacement and installation of road signs |
02 March 2014 |
| Housing |
Watson & Cox (Construction) Ltd |
Cedars Farm, Little Brington, Northamptonshire. |
foundations, oversites, drainage, access road, car parking & externals for a housing development of new build and barn conversions |
|
| Highways |
Carillion - WSP |
M1 J11-J13 Ditch Clearance |
Ditch clearance and regrading in both rural and urban locations along the M1 |
02 July 2014 |
| Highways |
Carillion - WSP |
A14 Ditch Clear- Leighton Bromswold |
Ditch clearance and regrading in rural locations along the A14 |
02 June 2014 |
| Housing |
SDC Construction |
Loves Farm, St. Neots, Cambs. |
bulk earthworks , trench fill & r/c groundbeam foundations,drainage - adopted and private, access roads - adopted & private, drives & footpaths, hard landscaping |
|
| Highways |
Carillion - WSP |
A1 Brampton to A1(M) Feede Pillar Access |
Lay-by, footpath, retaining walls & handrails for feeder pillar access |
02 May 2014 |
| Education |
SDC Construction |
Sharnbrook Upper School & College, Odell Road. |
bulk earthworks , trench fill & r/c foundations,drainage - adopted and private, access roads - adopted & private, footpaths, hard landscaping |
|
| Housing |
SDC |
Briscoe Rd, Loughborough |
foundations, oversites, drainage, car parking & externals for a housing development |
|
| Industrial |
Deejak |
Newton Trailers, Ridgmont |
foundations, drainage & slabs for a 1200 m2 heavy goods vehicle testing & repair centre |
|
| Leisure |
SDC Construction |
Bletchley Leisure Centre |
Bulk earthworks, foundations & groundfloor slabs, isitu concrete superstructure floor slabs, drainage- adopted and private, services, access roads, hard landscaping, multi storey car park. |
02 September 2014 |
|
Kier Marriott |
Stamford New College, Stamford |
Main entrance, circulation core, car park & externals |
|
|
Weldon |
Maplefields School, Corby, Northamptonshire |
New school building & sports hall, 6,500 m2, Associated drainage, car parking & externals. |
|
|
Willmott Dixon |
Kettering Science Academy |
New school campus. Associated drainage, car parking & externals. Bulk earthworks including engineered fill. |
|
|
Graham Construction |
Maplefields School, Corby |
New school building & sports hall, 6,500 m2, Associated drainage, car parking & externals. |
|
|
Carrilion WSP |
Soakaway remodelling A1(M) |
Reprofiling of 4 No. soakaways to increase capacity. Removal of non-hazardous material to remediation plant. |
|
| |
|
|
|
|
|